UTILITIES
Electric Service
JPEC 2010
W. KY RECC 2010
Natural Gas 2010
Water Service
Hickory Water District 2010
Existing Well 2007
On-Site Water
Treatment Plant 2010
Wastewater Service
Mayfield Elec. &
Water Systems 2010
New On-Site Facility 2010
Transportation
Roadways 2010
Air Service 2009
River Ports 2009
Rail Service 2010

WATER SERVICE: CONSTRUCTION

Hickory Water District has an existing 8” water main in the park area. This existing main has a capacity of 800 GPM and the water system has a current capacity of 1 MGD with no immediate plans to upgrade. Factoring in for peak utilization the system has an excess capacity of 0.55 MGD.

To extend this 8” main to the park is estimated to cost $750,000 and would require
about 300 days to complete.

Final construction is dependent upon tenant’s specifications.