HOME (Assessment Report)
|
ON-SITE WASTEWATER TREATMENT SERVICE: CONSTRUCTION
New Wastewater Service:
A new On-Site Wastewater Treatment facility could be constructed on the park property as an alternative to expansion of the Mayfield Electric & Water System. A new 2 MGD treatment facility could be constructed near the northeast corner of Tract 1 (North Section) of the park property with discharge to Mayfield Creek.
Time & Cost Estimates:
- 2.0 MGD on-site plant treatment facility - $10 million
- Lift Station - $1 million
- These new facilities would require approximately 24 months to complete
- (9 months for design & permitting and an additional 15 months for construction).
- Final construction is dependent upon the tenant’s specifications.
On-Site Wastewater Treatment Plant Map
|