HOME (Assessment Report)
Land Acquisition
Tract 1 (North) 2003-2005
Tract 2 (South) 2005-2007
Environmental
Phase I
Tract 1 2003 | 2009
Tract 2 2005 | 2009
Phase II
Tract 1 2003
Tract 2 2009
Geotechnical
Tract 1 2003
Tract 2 2005 | 2009
Wetland Delineation
Tract 1 2003 | 2008
Tract 2 2008
Archeological
Tract 1 2003 | 2009
Tract 2 2005 | 2009
Endangered Species
Tract 1 2003 | 2009
Tract 2 2009
Environmental Permitting 2010
UTILITIES
Electric Service
JPEC 2010
W. KY RECC 2010
Natural Gas 2010
Water Service
Hickory Water District 2010
Existing Well 2007
On-Site Water
Treatment Plant 2010
Wastewater Service
Mayfield Elec. &
Water Systems 2010
New On-Site Facility 2010
Transportation
Roadways 2010
Air Service 2009
River Ports 2009
Rail Service 2010

ARCHEOLOGICAL STUDY:
IN-PROGRESS (to be complete by 2010)

Tract 1 (North Section) -

UK Program for Archeological Research (UK-PAR) is presently preparing to survey approximately 370 acres that lies along the channelized Mayfield Creek and is a portion of Tract 1 (North Section) that was not surveyed in 2003. Also UK-PAR is to survey a 45 acre tract located south of Pittman Road, another tract that was not surveyed in 2003. This additional surveying to be conducted by UK-PAR should be completed in the fall of 2009 and will result in a combined Phase I and Phase II report. The Phase II portion of the report will target NRHP eligibility assessment for the World War II munitions factory.

Archeological Map